W SP and AECOM are currently fighting in a UK court over whether AECOM should pay for all or part of a $17-million settlement owed to the developer of a data center in Frankfurt, Germany.
Portsmouth, N.H.-based data center developer Iron Mountain signed up WSP for the design work in 2019. The project involved a four-story building shell with about 320,00 sq ft of data center space in three building modules, plus offices. The design work also included interior fit-out of the office area, 19,000 sq ft of data halls and a power and cooling system.
Time was of the essence, with Iron Mountain looking for a “design freeze” prior to signing a contract with its project general contractor by February 2020. But by March 2020, when the design was supposed to have produced a final set for the general contractor, Iron Mountain alleged, the design provided was incomplete and error-ridden.
At that time Iron Mountain claimed it had to set aside about $20 million as a contingency for design work still to be done that could increase construction costs, when “less than [$1.1 million] would have typically been required” on a project of similar magnitude.
The litigation started in the U.S. In a 2023 breach-of-contract lawsuit in New York federal court, Iron Mountain alleged that WSP’s
actions and inactions, and those of its sub-consultants, delayed the project’s completion and added costs. WSP denied the allegations but also made a claim against AECOM, which provided services including engineering design to WSP and Iron Mountain on the project.
Pre-trial discovery in New York dragged on until January this year, when Iron Mountain and WSP agreed via mediation that WSP would pay a roughly $17-million settlement.
WSP is now seeking roughly that amount from AECOM in a UK Technology and Construction Court, several media companies report.
Looking for quick answers on construction and engineering topics?
Try Ask ENR, our new smart AI search tool.
Ask ENR →
The company leasing the data center has never been publicly identified.
“Compressed delivery timelines, technical complexity and commercial sensitivity” may drive parties to a data center dispute “away from litigation and towards arbitration,” notes Solomonic, the UK-based litigation analytics platform.